Stormwater: As-Builts
SCDES requires the submittal of As-Builts under specific circumstances when it comes to land-disturbing activities associated with large and small construction sites. There are two (2) circumstances where the Department requires submittal of As-Builts. These circumstances are while submitting a Notice of Termination (NOT) for NPDES coverage that included the construction of permanent detention and/or retention structures, and when you are applying for NPDES coverage that includes using a pre-existing detention and/or retention structure to accept on-site flows. Other cases may arise where SCDES will request an As-Built.
As-Built Survey Requirements
- Include grades/contours/depths for pond(s)
- Elevations and dimensions of all outlet structures, including:
- Pipe and orifice inverts and diameters
- Weir elevations and dimensions
- Riser dimensions and elevations
- Emergency spillway dimensions and elevations
- Locations and inverts for all pipes discharging into the pond
- If the elevations or dimensions of the structures listed above do not match those used in the approved plans, a certification statement signed by the project's Registered is required. Under some circumstances, revised pond routing calculations will be asked to be submitted.
All As-Builts must be prepared by a South Carolina Licensed Land surveyor and must be provided for all previously approved detention ponds that will receive flows from new drainage areas.
For As-Builts that do not match the approved plans on record, the project's Registered Engineer must submit a certification statement indicating that the pond, as built, will function within all applicable standards provided. As-Builts that drastically differ from approved plans may be required to submit a new analysis of the pond routing.
Note: As-built survey and /or analysis must be submitted and accepted by the Department before a Notice of Termination (NOT) is submitted.