Overview

The CSXT Bramlett Road Site (Site) consists of five parcels in Greenville, South Carolina, including the former location of a Duke Power Manufactured Gas Plant (MGP), which covers 3.69 acres and is located at 400 South Bramlett Road, and a seven-acre unpermitted construction and demolition debris landfill (a/k/a Vaughn Landfill) downgradient of the former MGP property. The current owner of the landfill, the MGP, and other three parcels is CSX Transportation, Inc. (CSXT).


In 1917, Southern Public Utilities originally developed the manufactured gas plant. Ownership of the MGP transferred to Duke Power Company in 1939. The plant ceased operation in 1951 and the above-ground structures were demolished in the late 1950s. In 1997, Duke Power Company changed its name to Duke Energy Corporation, in September 2006, converted to Duke Power Company, LLC, and in October of 2006, changed its name to Duke Energy Carolinas, LLC. (hereinafter generally referred to as "Duke")

Manufactured gas was the predecessor to natural gas and was used to provide gas for lighting, heating, and cooking for the City of Greenville. The Duke Power MGP produced gas using the coal gasification process. This process resulted in the creation of a tar-like waste material that was often discharged to nearby ditches or surface water bodies. Coal tar waste from the Duke Power MGP was discharged into several ditches and eventually migrated across Bramlett Road to a property where, in 1988, an unpermitted landfill was located on the property 800 feet west of the intersection of Bramlett Road and West Washington Street, on the south side of Bramlett Road. The landfill is approximately six feet in depth and covers approximately seven acres. Waste from the MGP is present beneath the landfill.

Assessments

Duke conducted several investigations to assess the nature and extent of contamination at the Site. In 2002, Duke removed 61,000 tons of material from the former MGP property and replaced it with clean soil. Soil was excavated to a depth of three to six feet across the majority of the former MGP property.

Voluntary Cleanup Contract

On July 29, 2016, Duke Energy Carolinas, LLC (Duke) entered into Voluntary Cleanup Contract 16-5857-RP (VCC) with DHEC. Under the VCC, Duke will conduct an environment investigation of the Site and will evaluate alternatives for addressing the remaining contamination. The Groundwater Remedial Investigation began in 2017. Following that initial investigation, it was determined that additional investigation was needed. In 2018, an Addendum to the Groundwater Remedial Investigation was approved and completed. Data from the Addendum showed that a third phase of Groundwater Remedial Investigation was necessary. An additional Remedial Investigation Work Plan Addendum was submitted and approved by DHEC in July 2019. Duke Energy submitted the Remedial Investigation Report in June 2020.  DHEC approved the Remedial Investigation Report in September 2020.  

It was determined that additional investigation was needed to evaluate the former stormwater conveyance ditches. Duke Energy submitted a Remedial Investigation Work Plan Addendum in September 2020 which was approved by DHEC. Along with the additional remedial investigation work, Duke submitted plans to conduct aquifer performance testing (November 2020), forensic analysis of non-aqueous phase liquids in sediment and soil samples (December 2020), and to provide interim best management practices in the ditches and the outfall (March 2021).  Duke Energy submitted the Remedial Investigation Report Addendum in late July 2021. The Remedial Investigation Report Addendum was approved by DHEC in January 2022. Duke Energy submitted a Feasibility Study Work Plan in August 2022. The Feasibility Study Work Plan was approved in November 2022.  

Historical Documents

Below are historical documents relating to the previous investigations of the Site. These documents include work plans, investigation activities, remedial action plans, and other key documents. If you are interested in documents that appear on the Index but are not listed below, please contact the Department.

Date

Description

2025-02-04SCDES's Approval of Quarterly Progress Report 4th Quarter 2024
2025-01-14Quarterly Progress Report 4th Quarter 2024
2024-05-17June 6, 2024 Public Meeting Fact Sheet
2024-05-17Proposed Plan

2024-02-20

DHEC's Approval of Focused Feasibility Study, Revision 1

October 2023

Focused Feasibility Study, Revision 1

2023-05-18

DHEC's Approval of Semi-annual Monitoring Report #7

2023-05-17

Semi-annual Monitoring Report #7

2023-01-11

DHEC’s approval of the Semiannual Monitoring Report

2023-01-03

Duke’s Semi-annual Monitoring Report Appendix B/Lab Reports

2023-01-03

Duke’s Semi-annual Monitoring Report plus Appendices A, C, & D

2022-11-27

DHEC’s review of the Feasibility Study Work Plan

2022-10-19

DHEC's Approval of Quarterly Progress Report 3rd Quarter 2022

2022-10-14

Quarterly Progress Report 3rd Quarter 2022

2022-08-19

Feasibility Study Work Plan

2022-08-10

DHEC Request for Feasibility Study Work Plan

2022-07-14

DHEC's Approval of Quarterly Progress Report 2nd Quarter 2022

2022-07-07

Quarterly Progress Report 2nd Quarter 2022

2022-04-27

DHEC's Approval of Quarterly Progress Report 1st Quarter 2022

2022-04-15

Quarterly Progress Report 1st Quarter 2022

2022-03-21

DHEC's Approval of Duke's Semi-Annual Monitoring Report - Event 4

2022-03-15

Duke's Semi-Annual Monitoring Report - Event 4

2022-01-31

DHEC's Mountain View Baptist Church Neighborhood Soil Sampling Report

2022-01-27

DHEC's Approval of Remedial Investigation Report Addendum

2022-01-18

DHEC's Approval of Quarterly Progress Report 4th Quarter 2021

2022-01-15

Quarterly Progress Report 4th Quarter 2021

2022-01-06

DHEC's Approval of Semiannual Monitoring Report (Quarter 1 & Quarter 2 2021)

2021-12-17

Interim Surface Water Best Management Practice Construction Completion Report

2021-10-21

DHEC's Approval of Quarterly Progress Report 3rd Quarter 2021

2021-10-15

Quarterly Progress Report 3rd Quarter 2021

2021-09-01

Semiannual Monitoring Report (Quarter 1 & Quarter 2 2021)

2021-07-30

Remedial Investigation Report Addendum - Appendices available by request.

2021-07-19

DHEC's Approval of Quarterly Progress Report 2nd Quarter 2021

2021-07-12

Quarterly Progress Report 2nd Quarter 2021

2021-04-15

DHEC's Approval of Quarterly Progress Report 1st Quarter 2021

2021-04-14

Quarterly Progress Report 1st Quarter 2021

2021-03-30

DHEC Approval of Interim Surface Water Best Management Practice Work Plan

2021-03-26

Interim Surface Water Best Management Practice Work Plan

2021-03

Mountain View Baptist Church Area Soil Sampling Fact Sheet

2021-01-20

DHEC's Approval of Quarterly Progress Report 4th Quarter 2020

2021-01-19

Quarterly Progress Report 4th Quarter 2020

2021-01-12

DHEC's Approval of Forensics Analysis

2020-12-28

Forensics Analysis of NAPL, Sediment, and Soil from the Former Bramlette MGP Site and Surrounding Areas

2020-11-17

DHEC's Approval of Aquifer Performance Test Work Plan
DHEC's Monitoring Well Approval

2020-11-02

Aquifer Performance Test Work Plan 

2020-10-26

Quarterly Progress Report 3rd Quarter 2020

2020-09-01

DHEC's approval of the Remedial Investigation Report 

2020-09-01

DHEC's approval of the Remedial Investigation Work Plan Addendum (Storm Water Ditch Assessment) 

2020-08-27

Duke's Remedial Investigation Work Plan Addendum - Storm Water Ditch Assessment

2020-07-22

DHEC's Review of Quarterly Progress Report 2nd Quarter 2020

2020-07-22

Quarterly Progress Report 2nd Quarter 2020

2020-06-09

Remedial Investigation Report
Because this document is so large, it had to be divided into zipped folders. Please download ALL parts before attempting to unzip.

Part 1

Part 2

Part 3

Part 4

Part 5

Part 6

2020-04-09

DHEC's Review of Quarterly Progress Report 1st Quarter 2020

2020-04-09

Quarterly Progress Report 1st Quarter 2020

2020-01-31

DHEC's Review of Quarterly Progress Report 4th Quarter 2019

2020-01-15

Quarterly Progress Report 4th Quarter 2019

2019-10-23

DHEC's Review of Quarterly Progress Report 3rd Quarter 2019

2019-10-15

Quarterly Progress Report 3rd Quarter 2019

2019-08-06

DHEC's Review of Remedial Investigation Work Plan Addendum

2019-07-23

DHEC's Review of Quarterly Progress Report 2nd Quarter 2019

2019-07-15

Quarterly Progress Report 2nd Quarter 2019

2019-07-07

Remedial Investigation Work Plan Addendum Monitoring Well

2019-07-03

Remedial Investigation Work Plan Addendum

2019-04-24

DHEC's Review of Quarterly Progress Report 1st Quarter 2019

2019-04-15

Quarterly Progress Report 1st Quarter 2019

2019-01-15

Quarterly Progress Report 4th Quarter 2018

2018-04-13

Groundwater Remedial Investigation Work Plan Addendum

2017-02-20

Groundwater Monitoring Report November 2016

2016-11-14

Groundwater Remedial Investigation Work Plan

2016-09-19

Notice of Community Meeting 10-4-16

2016-08-01

Executed VCC 16-5857-RP

2010-06-10

Groundwater Monitoring Report

2010-03-04

Corrective Action Plan

2009-01-16

Groundwater Continuous Action Plan

2003-06-09

Remedial Action Plan Final Report—Volume 2

2003-06-09

Remedial Action Plan Final Report—Volume 1

2000-09-14

Remedial Action Plan

2000-06-30

Investigation & Site Assessment Report—Phase III, Volume 2

2000-06-30

Investigation & Site Assessment Report—Phase III, Volume 1

1997-03-21

Workplan--Phase III

1996-09-03

Site Investigation—Phase II

1996-08-17

Site Investigation: Soil Sediment & Groundwater Sampling

1995-08-01

Workplan: Site Investigation and Monitoring Well Installations

1994-10-01

Workplan: Soil Sediment & Groundwater Sampling

 

Mailing List

Anyone interested in receiving updates may contact Elisa Vincent at 803-898-0840 or via email Elisa.Vincent@des.sc.gov . If you have received information directly from DHEC, you are already on the Site's mailing list.